by Puru Miah | Aug 29, 2019 | Blog: All Things Mile End, All Things Tower Hamlets, Community
Update on works on Barlett Park, including stopping up on Cotall Street and temporary closure of grass football pitches. Please find below more details: Works to improve Bartlett Park are progressing well, although as I am sure you are aware, there have been some...
by Puru Miah | Jan 19, 2019 | Blog: All Things Mile End, All Things Tower Hamlets, Community
Bartlett Park works are starting on site this week. The work will be carried out in several stages to enable the park to remain open throughout. The works are due to be completed at the end of October 2019. The approximate phases are as follows: • January – end April...